Form 8-K · Current report

Ameren 8-K, filed Sep 28, 2026

Filed
CIK
0001002910
Accession no.
0001104659-26-111420
AI-generated summary

Summary

Union Electric Company, doing business as Ameren Missouri, filed its 2026 non-binding integrated resource plan with the Missouri Public Service Commission, outlining a preferred plan that adds natural gas, solar, wind, battery storage, and nuclear generation while retiring coal and certain natural gas capacity. The plan assumes load growth of roughly 2.9–3.9 GW by 2030, 5–6 GW by 2035, and 6–9 GW by 2045, and expects Ameren Missouri to seek and receive NRC approval to extend the Callaway nuclear energy center’s operating license beyond 2044.

Key points

  • The preferred plan includes adding 2,100 MW of combined-cycle natural gas by 2031, 1,900 MW of simple-cycle natural gas by 2029, 500 MW of natural gas fuel cells by 2030, 1,300 MW of solar by 2030, 1,500 MW of wind by 2040, 2,400 MW of battery storage by 2030, and 1,200 MW of new nuclear by 2040.
  • It extends the retirement date of two Labadie coal-fired units from 2036 to 2042 and retires about 1,800 MW of natural gas-fired energy centers by 2040.
  • The plan expects Ameren Missouri to seek and receive Nuclear Regulatory Commission approval to extend the Callaway nuclear energy center’s operating license beyond its current 2044 expiration date.
  • Ameren Missouri’s forecast for the preferred plan and high load growth scenarios ranges from about 2.9–3.9 GW by 2030, 5–6 GW by 2035, and 6–9 GW by 2045.

Written by an AI model from the filing text. It can be incomplete or wrong; the filing on SEC.gov is the record.

Items reported

  • 8.01Other Events

From the filing

ITEM 8.01 Other Events. On September 28, 2026, Union Electric Company, doing business as Ameren Missouri (“Ameren Missouri”), filed its non-binding integrated resource plan (“2026 IRP”) with the Missouri Public Service Commission (“MoPSC”). The 2026 IRP includes Ameren Missouri’s preferred plan for reliably meeting customers’ projected long-term energy needs in a least cost manner. The 2026 IRP reflects forecasted energy demand growth assumptions for the preferred plan and high load growth scenarios ranging from approximately 2.9 to 3.9 gigawatts (“GW”) by 2030, 5 to 6 GW by 2035, and 6 to 9 GW by 2045. …

An excerpt of the text as filed with the SEC, cut for length.

Readster writes AI-generated summaries of public filings for research purposes only. Summaries can be incomplete or wrong — check the original filing on SEC.gov before relying on it. Nothing here is investment, legal or medical advice.

Follow Ameren in Readster

Add Ameren to your watchlist and its SEC filings reach your brief alongside the news about it, every line cited to its source. Readster also follows topics, people, newsletters and podcasts.

No credit card. When the trial ends, you move to Readster Free unless you subscribe.